Invoice

From:
3278-240th Street,
Langley, BC,
V2Z 2J3
Tel: 604-308-1698

info@optimalcontracting.ca

Invoice Number INV-15151575
Invoice Date July 31, 2020
Due Date July 31, 2020
Total Due $24,465.00
To:
Strata VR 027, Highpointe,

2101 Whistler Road,
Whistler, B.C

Claim For Change in Contract Price

Hrs/Qty Service Rate/PriceAdjustSub Total
3 Labour rate for 3 days for 4 workers @ $75 p/h at 8 hours p/d

time delay framing upgrade

$2,400.000.00%$7,200.00
3 Accommodation

for 4 workers for an extra 3 nights @ $189 p/n for 2 rooms (2 people per room)

$378.000.00%$1,134.00
7 labour rate @$40 p/h for 8 hour per day x3

time delay overall project
labour rate for 1 extra week for 3 man crew

$960.000.00%$6,720.00
7 site foreman rate @$100 p/h for 8 hour per day
$800.000.00%$5,600.00
7 Accommodation

for 4 workers for an extra 7 nights @ $189 p/n for 2 rooms (2 people per room)

$378.000.00%$2,646.00
Sub Total $23,300.00
Tax $1,165.00
Total Due $24,465.00